Major Projects

MAJOR PROJECTS
S.No. Details of jobs, with name of the project/Site Contract Value In Crores Skilled/unskilled workers deployed at the project/site for the job (Approx) Contract Duration Percentage  Completion of the job
Current Running Projects
1 Fabrication, Erection & Alignment of Gas Duct and Structure from the ESP outlet to Cheminy Inlet with L&T MHPS @ Ghatampur Power Plant 8.75 50 2 Years Just Started
2 AG piping fabrication and erection work at IOCL haldia with Punj Lloyd 2.14 80 09months 60% till date
3 Fabrication & Erection of Structure Piping and Installation of Equipments with Adani at MSPVL 15 50 1 Year 95% till date
4 Structure Erection work at JSW dolvi 1.5 40 03 Months 50% till date
Completed Projects
5 Boiler Structure, Ducting, Rotary & Painting work at 5*800MW Tata power Mundra with IOTEP. 3.5 500 2years 100%
6 Boiler structure, Mill, Ducting, at 2*660MW Adani Power Kawai with Petron Engineering 2 300 1.5 Years 100%
7 Miscellaneous work(MOIS,Structure) at 2*660MW with Adani Power 1.5 100 2 Years 100%
8 Turbine piping work at 5*660MW Adani Power Tirora with U.B Engg 0.9 100 6 Months 100%
9 Rotary installation work at Maruti Clean coal power 0.35 30 4 Months 100%
10 Boiler Ducting, Structure, Mill, Fan, at 2*660MW with Petron 3 170 2 Years 100%
11 Structural, AG&UG piping, ducting fabrication & erectionwork at Mundra Solar (Adani) 14 700 1 Year 100%
12 Structural work steam super heater at Reliance Jamnagar with Linde Engineering 1.2 150 8 months 100%
13 AG & UG piping fabrication & erection work at JBF Petrochemical Ltd Mangalore with Petron 1.8 120 2 Years 100%